Works On Adaptation Of The Construcion Of The Pump Station Duklo In Municilaty Of Niksic

Construction works

  • Demolition works (carefully removed old steel doors and windows and sheet metal roof and all existing ceramic tiles). Roof covering with roof sandwich panels d=10cm; floors (ceramic tiles), wall reparations (filling of the old holes, plaster works, painting works) facade works, joinery works include changes of all doors and windows, sanitary equipment includes toilet and laboratory.

Electromechanical works

  • Replace of complete existing low-voltage electromechanical installation and design and installation of the new one including the lights

Project Details

  • Date:June 15, 2015